Period Client/Main Contractor Project Description of Work
Jan-09 –
Feb-09
CLP Power Hong Kong Ltd.
Black Point Power Station
Castle Peak Power Station
Inspection and cleaning of intake head grilles
Culvert Joint Sealing
Jan-09 –
Feb-09
Freyssinet Hong Kong Ltd.
Terminal 4 Berth 4 & 6
Supply and Installation of Galvanic Anodes
and Denso Tape Protection System
Dec-08 –
Jan-09
Friendly Benefit Eng. Ltd.
(Main Contractor: China
Harbour Engineering Co. Ltd.)
Quarry Bay
Sunken Barge: 梭駿 DL-6
Salvage of Sunken Barge
Dec-08
Friendly Benefit Eng. Ltd.
(Main Contractor: Chun Wo
Const. & Eng. Co. Ltd.
Peng Chau Submarine Outfall
CCTV inspection and repair of leakage
water pipe
Jan 2009 –
Dec-09
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service to
swimming pool
Jan-09
Meinhardt Consulting Engineers
Seawall behind Kennedy Town
Condition Survey for Pier Structure (Pier 3)
Dec-08
Jan 09
Sunny Construction & Marine
Engineering Co.
Aviation Fuel Receiving Facility at Sha
Chau
Maintenance Dredging in the Approach
Channel
Jul-08 –
Aug 08
Hong Kong Marine Contractors
Ltd.
CLP Power 132kV Submarine Cable
Circuit Installation between Ma On
Shan & Pak Shek Kok
Installation of 8 Nos. of HDPE duct under
the seawall, wave deflector and seabed
at Pak Shek Kok, Shatin Hoi
Jul-08
Discovery Bay Enterprises Ltd.
Discovery Bay Maintenance Centre,
Tsing Yi
Installation of steel bar on guide way of
lifting platform
May 08 –
Jun 08
Yee Kee Hong
Po Toi O, Sai Kung
Salvage of Sunken Barge “Kam Wu 22”
May 08 –
Oct 08
Penta Ocean Construction Co.
Ltd.
Modern Terminal Ltd.
Kwai Chung Container Port
Terminals 1, 2 & 5 Upgrading Works
Contract No. 8
Terminal 2 Strengthening Works
Jan 08 –
Feb-08
CLP Power Hong Kong Ltd.
Black Point Power Station
Castle Peak Power Station
Inspection and cleaning of intake head
grilles, dosing pipe at culvert, replace of
seawall blocks and culvert joint sealing
Jan 2008 –
Mar-08
Dixie Engineering Co. Ltd.
(Client: PCCW)
PWP Item No. 197CL Improvement to
existing roads and drains in Cheung
Chau Old Town Remaining
Eng. Works (Stage 3)
Locate the PCCWS Submarine Optical
Fiber Cables
Nov 07 –
Mar-08
CLP Engineering Ltd.
Hongkong International Airport
Seawater Pump Houses
No. 1, 1b and 5
Inspection and cleaning of intake chambers
and culverts Supply and install the addition
dosing pipeline
Nov 07 –
Dec-07
Discovery Bay Enterprises Ltd.
Discovery Bay Maintenance Centre,
Tsing Yi
Seabed Dredging Work
Nov-07
Mar-08
Electrical & Mechanical Service
Department
General Post Office Seawater pumphouse
Repairing of penstock of the sump
pit chamber
Nov 07 –
Dec-08
CPC Construction Hong Kong
Co. Ltd.
Shek Pai Wan Ice Plant
Seawater Pump Pits Cleaning
Nov 07 –
Dec-08
CPC Construction Hong Kong
Ltd.
Tai Chung Kau Bridge
Desilting of material inside a 90m culvert
Nov 07 –
Sep-08
Paul Y. Construction Co. Ltd.
(Client: The HK Electric Co. Ltd.)
Improvement Works for Lamma
Power Station
Cathodic Protection Works
Jan 2008 –
Dec-08
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service
to swimming pool
Sept 07 –
Oct-07
Hongkong International
Terminals
Terminal 4 Berth 4 and 6
Galvanic Anodes and Denso Tape
Protection System Inspection at Under
Quay Deck
Jul-07
Wai Kee (Zens) Construction &
Transportation Co. Ltd.
Modern Terminals Ltd.
Terminals 1, 2 & 5 Upgrading
Contract No. 7 – Deepening Dredging
Phase I
Check the thickness of mud along toe of
existing seawall
Jun 07 –
Jun-09
Welcome Construction Co. Ltd.
Drainage Maintenance and Construction in
Hong Kong Island and Islands Districts
(2006 – 2008)
Maintainence, CCTV inspection, hydrographic
survey and repairing workto DSD plants and
facilities in Hong Kong, Kowloon, New
Territories and Outlying Islands
Jun 07 –
Sept 07
Shun Chin Engineering Ltd.
West Region
Submarine Cable Work Audit Service
Jun 07
Chun Wo Construction &
Engineering Co. Ltd.
Contract No. 1/WSD/06(H)
Quarry Bay Salt Water Pumping Station
Design, supply and install of curtain to
prevent red tide floating into the intake chamber
May-07
Modern Terminal Ltd.
Kwai Chung Container Terminal No. 2
CCTV inspection and air-lifting work to the
seabed condition
May-07
TJ Engineering Services Ltd.
World Wide House
Penstock repair works to Pump Station
No. 16
Apr 2007 –
May-07
Smart Grand Engineering Ltd.
Kwai Chung Container Terminal No. 4
Erect of scaffolding platform underneath
the pier
Apr 2007 –
May-07
Victory Engineering Service Co.
Ltd.
Yaumatei Government Office Pumphouse
Sealing the water intake
Apr-07
Zhen Hua Shipping Co.
M/V “Zhen Hua 2”
Inspection of Cargo vessel
May-07
Pak Lik Engineering Ltd.
The HK Academy for Performing Arts
Installation and removal of bulkhead
Jan 2007 –
Feb-07
TJ Engineering Services Ltd.
Central MTR Pumping Station
Supply diver to assist underwater works
Jan 2007 –
Feb-07
Penta Ocean Construction Co. Ltd.
Contract No. DC/2002/02
Wanchai East & North Point Sewerage
Demolition of branch pipe
Supply diver to assist underwater works
Dec 2006 –
Feb-07
Friendly Benefit Engineering Ltd.
(Main Contractor: Chun Wo
Construction & Eng. Co. Ltd.)
North Point Pump House
Cut and float the pump house and mobilize
to Sai Kung as artifical reef
Dec 2006 –
Feb-07
Electrical & Mechanical Services
Department
EMSD Services Section
General Post Office Seawater Pumphouse
Clearing and removal the rid of debris from
penstock guide rail and sump pit chamber
Repair 2 nos. of penstock
Jan 2007 –
Dec-07
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service to
swimming pool
Dec 2006 –
Jan-07
The Hong Kong Ice & Cold
Storage Co. Ltd.
Yau Tong Ice Plant
Castle Peak Ice Plant
Removal of all sediments, marine growths
and rubbish in the sea water inlet pipes
and pump pits
Oct 2006 –
Dec-06
Shiu Wing Steel Ltd.
Shiu Wing Steel Mill at Tuen Mun Area 38
Works to Seawater Intake Chamber
Design, supply and installation of bulkhead
Cleaning of the intake chamber
Repair the concrete wall
Seabed survey
Oct 2006 –
Dec-06
Penta Ocean Construction Co. Ltd.
Contract No. DC/2002/02
Wanchai East & North Point Sewerage
Design & build of bulkhead
Provide qualified diving team to assist
underwater works
Jun 2006 –
Jul-06
Hongkong International
Terminals Ltd.
Kwai Chung Container Terminal
Berth 4 & 6
Galvanic Anodes Inspection at Underdeck
Aug 2006 –
Sep-06
Paul Y Construction Co. Ltd.
Contract No. DC/2004/09
Building and Civil Maintenacne and Minor
Works to DSD Plants and Facilities
‘(2005-2007)
Maintenance works for Shek O Sewer Tunnel
Apr-06
Po Wing H.P. Drainpipe &
Construction Co. Ltd.
Kowloon Station Pumphouse
Removal of bulkhead, guiderail and bolts
at inlet
Feb 2006 –
Jan-07
Friendly Benefit Engineering Ltd.
Kwai Chung Container Terminal 1, 2 and 5
Steel thickness and photography to piles
Piles repairing and upgrading works
Jan 2006 –
Dec-06
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service
to swimming pool
Oct 2005 –
Jan-06
Camell Engineering Int. Co. Ltd.
Kwai Chung Container Terminal 4
Berth 6
Installation and demolition of temporary
platform
Aug 2005 –
Jun-2007
Chung Shun Construction Ltd.
(Main Contractor: Paul Y
Construction Co. Ltd.)
Contract No. DC/2004/09
Building and Civil Maintenacne and Minor
Works to DSD Plants and Facilities
‘(2005-2007)
Maintainence, inspection and repairing work
to DSD plants and facilities in Hong Kong,
Kowloon, New Territories and Outlying Islands
Dec 2005 –
Jan-06
Bekk Solutions
Central Reclamation
Provide qualified diving team to assist
underwater works inside confined space
culvert Provide qualified diving team to assist
underwater works at Station C
Oct 2005 –
May-06
Modern Terminals Ltd.
Terminals 1, 2, and 9
CCTV inspection to toe of Terminals 1 & 2
Pile thickness measurement for Terminal 5
Fender block inspection for Terminal 9
Oct 2005 –
Nov-05
China Resources Petrochems
(Group) Co. Ltd.
CRC Oil Terminal, Tsing Yi
Echo sounding survey to tanker pier
CCTV inspection to raking and sheet piles
Sept 2005 –
Oct-05
宏俊工程有限公司
Kwai Chung Container Terminal
Berth 6
Install and demolish a temporary platform
Jul-05
Johnson Controls Hong Kong
Ltd
Provident Centre, North Point
CCTV inspection to the band screen, stoplog
Clean up the desilting material
Jul 2005 –
Sep-05
Electrical & Mechanical
Services Department
Tsuen Wan Town Hall Seawater pump house
Kau Shat Wan Explosive complex
Cleaning of Seawater Chambers
Inlet block up jobs for replacement of
300mm gate valves
Jun 2005 –
Aug-05
Corrpro Companies Far East
Ltd
Kwai Chung Terminal Berth 4 and 6
Galvanic anode inspection at Underdeck of
Berth 4 & 6
June 2005 –
Jul-05
The World Wide Diving Contractor
Co. Ltd.
(Main Contractor: Saipem Asia
Sdn. Bhd.)
Lamma Power Station Ext.
Burying of submarine gas pipeline from Tai
PanWan to Lamma Power Station
Mar 2005 –
Jun-05
Strong Basic Engineering Ltd.
Minor works Contract No. 2004T050
Shaukeiwan Preliminary Treatment Works
Installation of non-return valves to the outfall
(water depth: -42mpd)
Jan 2005 –
Dec-05
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service to
swimming pool
Dec 2004 –
Feb-05
Corrpro Companies Far East
Ltd
Chek Lap Kok International Airport
Install and weld the anodes at the Control
Light Tower
Nov 2004 –
Apr-05
Leader Marine Contractors Ltd.
Contract No. 03/8013
Additional Transmission System for
Supply and Installation of Precast Concrete
Slipways, Retaining Walls and Blocks
Aug 2004 –
Sep-04
Tai Loy Engineering Co. Ltd.,
Kwai Chung Container Terminal No. 4
CCTV inspection and measurement
of anodes
Feb 2004 –
Jan-05
Hyundai – CCECC Joint Venture
Kwai Chung Container Port
Terminal 9 Development
Supply diving team to assist
underwater works
Jan 04 –
Apr-04
Friendly Benefit Eng. Ltd.
Hong Kong Disneyland Project
Laying of precast concrete slab at the roof
of the pier
Jan-04
May-04
Hong Kong Land & Marine
Contractor Ltd.
132kV submarine cables installation
between Tai Long Wan and Cheung Chau
Excavation of breakwater
Levelling and screeding pipe duct bedding
Installation of HDPE pipe ducts and sinkers
Backfill and reinstate the excavated section
Jan 2004 –
Dec-04
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service
to swimming pool
Dec 2003 –
Sep-05
Camell Engineering Int. Co. Ltd.
(Main Contractor: Paul Y – ITC
Construction Co. Ltd.)
Contract No. DC2002/15
Building and Civil Maintenance and
Minor Works to DSD Plants and
Facilities (2003-2005)
Maintainence, inspection and repairing work
to DSD plants and facilities in Hong Kong,
Kowloon, New Territories and Outlying
Islands
Dec 2003 –
Jan-04
Hong Kong Land & Marine
Contractor Ltd.
11kv Submarine Cable from Tai Mong Chai
to Kiu Tsui
Laying of concrete slab for installation
of submarine cable
Jan 2003 –
Dec-03
P & A Engineering Ltd.
Shing Mun Valley Swimming Pool
Kowloon Park Swimming Pool
CCTV inspection and cleaning service
to swimming pool
Jun 2003-
Jan-05
Paul Y.-Penta Ocean Joint
Venture
Lamma Power Station Extension
Installation of rubber fender and anchor
Desilting and removal of blockage inside
the existing culvert
Aug-03
Tai Loy Engineering Co. Ltd.,
Kwai Chung Container Terminal No. 4
CCTV inspection and measurement of
anodes
Mar 2003 –
Aug-04
Friendly Benefit Eng. Ltd.
Kwai Chung Container Port
Terminal 9 Development
Supervision of precast concrete unit
construction Installation of intake chamber
Mar – Apr
2002
Kwan Shing Eng. & Const.
Co. Ltd.
Kwai Chung Terminal No. 3
Installation of Denso Seashield for pile
Feb – Mar
2002
Rich Sea Construction Eng.
Co. Ltd.
Contract No. RP/04/96
PIS Minor Rural Improvement Works
Package ID
Cut off and clear away the head of the I-beam
and debris Underwater cutting of tubular
pipe and I-beam Underwater cutting of a
300 x 300 hole at the pile cap+E203
Jan – Aug
2002
Hong Kong Land Marine
Contractor Ltd.
Installation of reinforcement concrete
slab protection to CLP 132 kV submarine
cable circuit – Sai Kung / Po Lam
Installation of reinforcement concrete slab
Jan 2002 –
Dec-02
Welcome Construction Co. Ltd.
Drainage Maintenance and Construction in
Hong Kong Island and Islands Districts
(2002 – 2004)
Underwater survey, CCTV inspection work
and desilting work inside confined
space culvert
Oct 2001 –
‘Mar 2002
Friendly Benefit
Engineering Ltd.
Contract No. HCC00/8016
Lamma Power Station Extension
Levelling and installation of 7 Nos.
culvert, 1 No. intake chamber, 2 Nos. of
outfall and 4 Nos. of retaining wall
Feb – Nov
2001
Leighton Contractors (Asia)
Ltd.
Engineering Infrastructure for Cyberport
Development
Installation of submarine outfall
Dec 2000 –
Oct-03
Penta-Ocean – Kier Joint
Venture
KCRC West Rail, Contract No. CC-300
Development Sewage Submarine Outfall
Installation of Precast Units and Cast In-situ
units of Box Culvert Removal of 3 steel
pipes (dia. 1.8m) of WSD Interim Water Intake
To demolish and reinstate of seawall at Ma
Tau Pa and Tai Hoi Culvert
Sealing wall inside culverts, cutting back
existing culvert cells, approved rockfill and
associated works including reinstatement of
all disturbed existing structured and finishes
to original at existing Ma Tau Pa and Tai Ho
Culverts
Sandfilling to the gap between D/W and tunnel
roof upto 750 mm at North Tunnel Installation
of seawall block at Tai Chung Kiu Seawall
Grouting work at Stitch Joint at Tai Ho Culvert
Apr-Sept
2000
Friendly Benefit Eng. Ltd.
(Main Contractor: Paul Y
Contractors Ltd.)
Contract No. CHEC125
Advance works for Cyberport Development
at Telegraph Bay
Installation of Precast Units and
Cast In-situ units of Box Culvert
2000-2002
Mott MacDonald HK Ltd.
Contract No. NL9/98
North Lantau Development
Tung Chung Development, Phase 3A
Reclamation for Areas 51, 52 (Part) to 56
Independent diving inspection to all the
related marine works
1999-2003
Goodview Const. Eng. Ltd.
(Consultant: Maunsell
Consultants Asia Ltd.)
Contract No. HY/98/02
Widening of Tolo Highway between
Island House and Ma Lui Shui Interchange
Independent diving inspection to all the
related marine works
1999-2000
Friendly Benefit Eng. Ltd.
(Main Contractor:
China Harbour Eng. Co. Ltd.)
Contract No. CC302
KCRC West Rail
Installation of Ma Tau Pa Culvert and Tai Ho
Culvert Installation of 2250 intake
Installation of 1800 temporary intake pipeline
Demolition of the Old Ferry Pier
Dismantle and removal of steel frame
bulkhead at Ma Tau Pa Culvert and Tai
Po Culvert
1999
NEC Corporation
TPKM2 systems project in Taiwan
Laying of submarine cable and landing
support work
1999
HK Telecom Ltd.
S. Lantau Island, Deep Water Bay,
Cape DAguilar
Inspection of submarine cables
1999
Sun Fook Kong (Civil) Ltd.
To Kwa Wan Sewerage Plant
CCTV inspection of submarine pipeline
and damaged gap
1999
Dragages-Zen Pacific Joint
Venture
Contract No. DCRC DB320
Kwai Tsing Tunnel
Investigation of pile inside D-nullah
1998
Aoki Corporation
Culvert in Mongkok
Inspection and repairing of water leakage to
the drainage pipe and miscellaneous work
1998
NEC Corporation
Submarine cable laying from Taiwan to USA
(Taiwan Section)
Submarine cable landing support work
1997-1998
Hang Da Eng. Co.
Victoria Permanent Pier No. 61
New Praya, Kennedy Town
Demolition of Pier, underwater pile cutting
and installation of warning marker buoy
1997
Welcome Eng. Co. Ltd.
River Trade Terminal Area 38
CCTV inspection to Pillar Point Sewage work
Inspection and repairing of leakage to the
existing outfall
1997
Welcome Eng. Co. Ltd.
Contract DC/95/02
Mainland North Districts 96-98
Drainage maintenance and construction
1997
Aoki Corporation
Contract UA19/93
Diving work in stagnant water inside box
culvert at Mongkok
CCTV inspection inside the box culvert
1996-1997
Kinord Engineering Co. Ltd.
Contract DC/94/13
Construction of Sandy Bay Sewage plant
and submarine outfall
Installation of 600Ø HDPE submarine
pipeline and outfall
1996-1997
The Nippon Salvage Co. Ltd.
CLP Contract No. 459617/AL and
459906/AL
New Airport Navigation Aid (Phase 1 & 2)
Supply, install and repairing of 11kv
submarine cables and CCTV inspection
1995-1996
NKK Corporation
Contract EP7D/TP23/1392/93
Lantau Link
Installation of submarine gas pipeline
CCTV inspection to all the related
marine works
1994-1996
Po Wing Drainage Const.
Co. Ltd.
Cha Wan Plant, Tai O Plant,
Apleichau Plant, Tsing Yi Plant
CCTV inspection to submarine outfall of the
screening plant and the related remedial
works
1995
Hsin Chong Const. Co. Ltd.
Contract No. 207
Stonecutter Island Project
Independent diving inspection to marine
works and pumphouse
1995
Water Supplies Dept.
Contract No. 2/WSD/93
Peng Chau to Chow Kung Island
Underwater inspection of HDPE submarine
pipeline and pipeline repairing
1994-1997
Dragages-Penta-BSG Joint
Venture
Contract UA11/91
Central Reclamation Phase I
Installation and CCTV inspection to Immersed
Tube Unit Installation and CCTV inspection
to 4 pumphouses Concrete repairing to piles
of Pier No. 3, 4, 5, 6 and 7 Coring and concrete
repairing to piles of Pier 1, 3, 4, 5, 6 & 7
Related marine works
1994-1995
Gammon Construction Ltd.
Contract No. EP/SP/9/91
Nim Wan, West NT Landfill
Independent diving inspection to the
related marine works
1994
Kumagai Gumi (HK) Ltd.
Contract SC-002
Western Harbour Crossing
Submarine outfall installation and
underwater blasting
1993-1994
Chun Wo Construction Co. Ltd.
Contract No. DC/90/08
Stanley Bay
Independent diving inspection to the
related marine works
1993
Babtie Oakervee
Contract No. 1280/04
Tolo Harbour
Diving inspection to HKCGC submarine
gas pipeline
1993
Wesson U/W SVC
Contract CV/91/02
Reclamation of Yau Ma Tei Typhoon
Shelter
Laying of geotextile and the related
marine works
1993
Wai Kee Eng. Co. Ltd.
Ap Lei Chau Project
Installation of seawall blocks
1993
The HK Electric Co. Ltd.
Aberdeen to Ap Lei Chau
Laying of 275kv, 132kv, 110kv
submarine cable
1993
Segger Engineering
Old Sham Shui Po Pier
Floating of a sunken barge and
underwater cutting
1992-1993
Hanison Construction Co. Ltd.
Discovery Bay
Installation of precast concrete blocks to
form the vertical seawall
1992
Mott MacDonald HK Ltd.
Tsing Ma Bridge
Independent diving inspection to related
marine works
1992
Aoki Corporation
Contract No. CV/89/02
Shaukeiwan HDPE submarine outfall
Installation of 700mm Ø HDPE
submarine outfall
1991
Aoki Corporation
Contract No. 141 of 1986
New Shaukeiwan breakwater
Installation of twin cell box culvert
1990
NKK Corporation
Contract No. 24/WSD/87
Victoria Harbour (From Cha Kwo Ling
to Quarry Bay)
Laying of 1,700m submarine pipeline
1990
NKK Corporation
Contract No. EP & D/DP182/1236/9
Eastern Harbour Gas Pipeline
Installation of 1,700m gas pipeline from Cha
Kwo Ling to Quarry Bay